Santillana

For the execution of Buró Milla de Oro Santillana, a successful implementation of formwork on VR tables was achieved, increasing by 55% the weekly production of concrete slabs.
Reduction of 22% of man-hours per m2 of concrete slabs, achieving up to 9HH/m2.
Implementation of precast concrete stair flights, that ease an early delivery of this project.

Area:

19.947m2

Budgeted time

15 Months

Final executed time

15 Months

Budgeted value

$34.900 Mill

Final value executed

$27.900 Mill

Advance delivery

100% De acertividad en tiempo

Saved

$7.000 Mill

How did we do it?

Integration of services

  • Structuring
  • Investment
  • Design
  • Construction
  • Provision
  • Operatio
  • Digitalization of design models zero rework

Shorter time

employed on construction and design time

Lower cost

Zero rework

Meet our success stories

Success stories

DCIM104MEDIADJI_0022.JPG

Buró 25

Success stories

edificio-nova4

Nova Building

Success stories

avianca1

Avianca Building

Success stories

buro-santillana7

Santillana

Success stories

colgate-palmolive-6

Colgate Palmolive Distribution Center

Success stories

granplaza

El Ensueño Shopping Center