Home › Avianca Building
Success stories
Avianca Building
A corporate building was built for the Avianca company, in which the technical schools of operation, maintenance, dangerous goods and ground operations are located, it has 6 bays for flight simulators with a swimming pool.

Area:
34.263m2
Budgeted time
25 months
Final executed time
25 months
Budgeted value
$72.000 Mill
Final value executed
$72.000 Mill
Advance delivery
Saved
$0 Mill






How did we do it?
Integration of services
- Structuring
- Investment
- Design
- Construction
- Provision
- Operation
- Digitalization of design models ZERO REWORK
Shorter time
employed on construction and design time