Success stories
Hilton Corferias Hotel
For Hilton Corferias, compared to other projects with similar characteristics, there was a 37% increase in prefabrication of superstructure.
Area:
51.652m2
Budgeted time
31 Months
Final executed time
34 Months
Budgeted value
$190.000 Mill
Final value executed
$186.000 Mill
Advance delivery
90 Días
Saved
$4.000 Mill
![hilton-corferias](https://conconcreto.com/wp-content/uploads/elementor/thumbs/hilton-corferias-pu6geeleqh4iliv3h3zqvyz3ktxdghjdfrjb3q5zd4.jpg)
![hilton-corferias2](https://conconcreto.com/wp-content/uploads/elementor/thumbs/hilton-corferias2-pu6gehexaz8dkcr00n7mlg9hczjh3kukg5hrjk1sug.jpg)
![hilton-corferias3](https://conconcreto.com/wp-content/uploads/elementor/thumbs/hilton-corferias3-pu6gel6a2bdiusljeou4vfbbqj0xyd9hso3pgnw85k.jpg)
![hilton-corferias4](https://conconcreto.com/wp-content/uploads/elementor/thumbs/hilton-corferias4-pu6genzsmthdtmhfy820kwlpion1lgkot225whs1mw.jpg)
![hilton-corferias5](https://conconcreto.com/wp-content/uploads/elementor/thumbs/hilton-corferias5-pu6gerr5e5mj42bzc9oiuvnjw84ig8zm5ko3tlmgy0.jpg)
![hilton-corferias6](https://conconcreto.com/wp-content/uploads/elementor/thumbs/hilton-corferias6-pu6geuknynqe2w7vvswekcxxodqm3cat5ymk9fiafc.jpg)
![hilton-corferias7](https://conconcreto.com/wp-content/uploads/elementor/thumbs/hilton-corferias7-pu6gexe6j5u91q3sfc4a9u8bgjcpqfm06cl0p9e3wo.jpg)
How did we do it?
Integration of services
- Structuring
- Investment
- Design
- Construction
- Endowment
- Endowment
- Digitization of Design Models ZERO REWORK
Shorter time
employed on construction and design time