Hilton Corferias Hotel

For Hilton Corferias, compared to other projects with similar characteristics, there was a 37% increase in prefabrication of superstructure.

Area:

51.652m2

Budgeted time

31 Months

Final executed time

34 Months

Budgeted value

$190.000 Mill

Final value executed

$186.000 Mill

Advance delivery

90 Días

Saved

$4.000 Mill

How did we do it?

Integration of services

  • Structuring
  • Investment
  • Design
  • Construction
  • Endowment
  • Endowment
  • Digitization of Design Models ZERO REWORK

Shorter time

employed on construction and design time

Lower cost

Zero rework

Meet our success stories

Success stories

DCIM104MEDIADJI_0022.JPG

Buró 25

Success stories

edificio-nova4

Nova Building

Success stories

avianca1

Avianca Building

Success stories

buro-santillana7

Santillana

Success stories

colgate-palmolive-6

Colgate Palmolive Distribution Center

Success stories

granplaza

El Ensueño Shopping Center